Title
520-2609 – E Range & F Range Duct Sewer Main Relining
Reference number
cb-994-64198920
Solicitation number
52000-26-5480964
Publication date
2026-08-24
Tender closing date
2026-09-15T13:00:00
Expected contract start date
2026-09-18
Expected contract end date
2027-03-31
Unspsc
*72141120
*81141807
Unspsc description
*Sewer line construction service
*Plumbing or sewer inspection service
Procurement category
*CNST
Notice type
Request for Proposal
Procurement method
Competitive - Open bidding
Selection criteria
Lowest Price
Trade agreements
*Canadian Free Trade Agreement (CFTA)
Regions of opportunity
*Prince Albert
Regions of delivery
*Prince Albert
Contracting entity name
Correctional Service of Canada (CSC)
Contracting entity address line
3427 Faithfull Ave
Contracting entity address city
Saskatoon
Contracting entity address province
Saskatchewan
Contracting entity address postal code
S7K 8H6
Contracting entity address country
Canada
Contact info name
K•••••••• B••••
Contact info email
P••••••••@•••••••.••.ca
Contact info phone
(306) •••-••••
Contact info address line
•••• •••••••• •••
Contact info city
••••••••
Contact info province
••••••••
Contact info postalcode
••• •••
Contact info country
••••••
Attachment
https://canadabuys.canada.ca/sites/default/files/webform/tender_notice/104689/2026-08-24-1-25-invitation-to-tender-english_1.pdf,https://canadabuys.canada.ca/sites/default/files/webform/tender_notice/104689/2026-08-24-11-49-npp-english_0.pdf
Tender description
520-2609 E Range & F Range Duct Sewer Main Relining
This requirement is for: The Correctional Service of Canada, Saskatchewan Penitentiary in Prince Albert, Saskatchewan.
Trade agreement: Canadian Free Trade Agreement (CFTA).
Policy on Reciprocal Procurement: This solicitation is open only to Canadian suppliers.
Competitive Procurement Strategy: lowest priced compliant bid.
Set-aside under the Procurement Strategy for Indigenous Business: This procurement is not subject to any set-asides for Indigenous Suppliers.
Comprehensive Land Claim Agreement: This procurement is not subject to a Comprehensive Land Claims Agreement.
Security Requirements: This contract does not include security requirements.
Nature of Requirements:
The following is a summary of the statement of work for this requirement.
The Correctional Service Canada has a requirement to rehabilitate the existing sanitary sewer main within E & F ducts using cured in place pipe (CIPP) technology.
Objectives: To rehabilitate the existing sanitary sewer main within E & F ducts using cured in place pipe (CIPP) technology to restore structural integrity, eliminate infiltration and exfiltration, and extend service life with minimal disruption to operations.
Deliverables: the Contractor must keep site Disruptions (including, but not limited to noise, dust and smells) to a minimum. The Contractor must communicate all anticipated disruption to the Project Authority ahead to allow CSC to distribute communications.
1. Schedule:
a. The Contractor must perform the work during Saskatchewan Penitentiary’s regular business hours from Monday – Friday, 08:00 – 16:00
b. The Contractor must provide a Detailed Schedule upon contract award.
2. While on site, the contractor and sub-contractors must cooperate fully with operational staff and conform to all security requirements.
3. The Contractor must provide Operation and Maintenance (O&M) Manuals, that include the following information as a minimum:
a. Manufacturer product data
b. Maintenance Schedule
c. Warranty information
4. The Contractor must submit the operations and maintenance (O&M) manuals for CSC’s acceptance as a condition of Substantial Completion.
5. The Contractor must provide the following Drawings and Attachments:
a. Pre and post installation closed-circuit television (CCTV) video recordings.
b. Installation logs, curing records, quality assurance and quality control (QA/QC) documentation.
c. As-built records showing lined sections and reinstated connections.
d. Detailed progress pictures before and after cleaning.
e. Detailed progress pictures after completion.
f. Final CCTV Inspection with written acceptance by the Project Authority.
Any conditions for participation of suppliers not specified in solicitation documentation: None.
Estimated quantity of commodity: See solicitation document statement of work and basis of payment.
Duration of Contract and Time Frame for Delivery:
Construction Time:
The Contractor must perform and complete the Work within twenty-six (26) weeks.