Trade Agreement: WTO-AGP/NAFTA/AIT/Canada FTAs with
Peru/Colombia/Panama
Tendering Procedures: All interested suppliers may submit a bid
Attachment: None
Competitive Procurement Strategy: Lowest/Lower Bid
Comprehensive Land Claim Agreement: No
Nature of Requirements:
Snow Clearing/Landscape Maintenance CFS Leitrim, 3545 Leitrim
Road, Ottawa EP305-150806/A
Hill, Cris Telephone No. 819-956-1343 Fax No. 819-956-3600
c••••••••@•••••.••.ca
-----------------------------------------------------------------
-----------------------------------------------------------------
--------
Soliciation Amendment 005:
This Amendment is raised to Extend the closing date to April 22,
2015 at 2:00pm and amendment will follow shortly.
-----------------------------------------------------------------
-----------------------------------------------------------------
-
Soliciation Amendment 004:
This amendment is raised to (1) revise Security Clause from
Secret to Reliability Status at 7.3.1 and (2) revise Annex C -
SRCL as follows:
(1) revise Security Clause at 7.3.1
Delete in its entirety Security Clause at 7.3.1
Insert Revised Security Clause 7.3.1
1. The Contractor/Offeror must, at all times during the
performance of the Contract/Standing Offer, hold a valid
Designated Organization Screening (DOS), issued by the Canadian
Industrial Security Directorate (CISD), Public Works and
Government Services Canada (PWGSC).
2. The Contractor/Offeror personnel requiring access to
sensitive work site(s) must EACH hold a valid RELIABILITY
STATUS, granted or approved by CISD/PWGSC.
3. Subcontracts, which contain security requirements, are NOT to
be awarded without the prior written permission of CISD / PWGSC.
4. The Contractor/Offeror must comply with the provisions of the:
a) Security Requirements Check List and Security Guide (if
applicable), attached at Annex C;
b) Industrial Security Manual (Latest Edition).
(2) revised Annex C - SRCL
Delete in its entirety Annex C - SRCL
Insert Revised Annex C - SRCL (see attached)
*****************************************************************
**********************************************
Soliciation Amendment 002:
This amendment is raised to (1) revise the Mandatory Site Visit
date and revise the date of submission of Names and (2) revise
the closing date as follows:
(1) revise the Mandatory Site Visit date and revise the date of
submission of Names
Delete in its entirty:
2.6 Revised Mandatory Site Visit
INSERT
2.6 2nd Revised Mandatory Site Visit
It is mandatory that the Bidder or a representative of the
Bidder visit the work site. Arrangements have been made for the
site visit to be held at3545 Leitrim Rd, CFS LeitrimonApril 2,
2015 The site visit will begin at9:00am EDT, at the main
entrance/guard hut.
Personnel security screening is required prior to gaining
authorized access toCFS Leitrim, 3545 Leitrim Road. Bidders
must communicate with the Contracting Authority no later than
March 26, 2015, close of business dayto confirm attendance and
provide the Company Name, name(s) of the person(s) and their
cell phone number and company telephone number of who will
attend the site visit.
Bidders will be required to sign an attendance sheet. Bidders
should confirm in their bid that they have attended the site
visit. Bidders who do not attend the mandatory site visit or do
not send a representative will not be given an alternative
appointment and their bid will be declared non-responsive. Any
clarifications or changes to the bid solicitation resulting from
the site visit will be included as an amendment to the bid
solicitation.
No electronic devises are permitted on site (i.e. cell phones,
pagers, etc....)
A maximum of two (2) representatives per bidder will be
permitted to examine the sites
(2) revise the closing date
Closing date will be extended to close April 15, 2015 at 2:00pm
EDT.
ALL OTHER TERMS & CONDITIONS SHALL REMAIN THE SAME
*****************************************************************
*****************************************************
This Soliciation Amendment 001 is raised to revise the Mandatory
Site Visit as follows:
Delete in its entirty: 2.6 Mandatory Site Visit
INSERT
2.6 Revised Mandatory Site Visit
It is mandatory that the Bidder or a representative of the
Bidder visit the work site. Arrangements have been made for the
site visit to be held at3545 Leitrim Rd, CFS LeitrimonMarch 12,
2015 The site visit will begin at9:00am EDT, at the main
entrance/guard hut.
Personnel security screening is required prior to gaining
authorized access toCFS Leitrim, 3545 Leitrim Road. Bidders
must communicate with the Contracting Authority no later than
March 5, 2015, close of business dayto confirm attendance and
provide the Company Name, name(s) of the person(s) and their
cell phone number and company telephone number of who will
attend the site visit.
Bidders will be required to sign an attendance sheet. Bidders
should confirm in their bid that they have attended the site
visit. Bidders who do not attend the mandatory site visit or do
not send a representative will not be given an alternative
appointment and their bid will be declared non-responsive. Any
clarifications or changes to the bid solicitation resulting from
the site visit will be included as an amendment to the bid
solicitation.
No electronic devises are permitted on site (i.e. cell phones,
pagers, etc....)
A maximum of two (2) representatives per bidder will be
permitted to examine the sites
ALL OTHER TERMS & CONDITIONS SHALL REMAIN THE SAME
-----------------------------------------------------------------
-----------------------------------------------------------------
-----
Summary
Requirement - To provide Snow Removal Service and Landscape
Maintenance services including all
labour, material, equipment, supervision and transportation in
accordance with the Statement of Work
attached at Annex A.
Client Department - For Public Works and Government Services
Canada (PWGSC) at, CFS Leitrim,
3545 Leitrim Road, Ottawa, Ontario, Canada.
Period of contract - The period of any resulting Contract will
be for a period of one (1) year (estimated commencement date May
1, 2015) with Canada retaining an irrevocable option to extend
the contract for a period of four (4) additional consecutive
twelve (12) month periods.
Mandatory Site Visit
It is mandatory that the Bidder or a representative of the
Bidder visit the work site. Arrangements have been made for the
site visit to be held at3545 Leitrim Rd, CFS LeitrimonMarch 12,
2015 The site visit will begin at9:00am EDT, at the main
entrance/guard hut.
Personnel security screening is required prior to gaining
authorized access toCFS Leitrim, 3545 Leitrim Road. Bidders
must communicate with the Contracting Authority no later than
March 5, 2015, close of business dayto confirm attendance and
provide the name(s) of the person(s) and date of births of who
will attend the site visit.
Snow Clearing/Landscape Maintenance CFS Leitrim, 3545 Leitrim
Road, Ottawa EP305-150806/A
Hill, Cris Telephone No. 819-956-1343 Fax No. 819-956-3600
c••••••••@•••••.••.ca
-----------------------------------------------------------------
-----------------------------------------------------------------
--------
The Bidder's Company Security Officer (CSO) must ensure that
their representatives hold a valid security clearance at the
required Secret level for the site visit which is. Failure to
comply with the security requirements will result in the
representative(s) being denied access to the site.
Bidders will be required to sign an attendance sheet. Bidders
should confirm in their bid that they have attended the site
visit. Bidders who do not attend the mandatory site visit or do
not send a representative will not be given an alternative
appointment and their bid will be declared non-responsive. Any
clarifications or changes to the bid solicitation resulting from
the site visit will be included as an amendment to the bid
solicitation.
A maximum of two (2) representatives per bidder will be
permitted to examine the sites
Security Requirement
1. The Contractor/Offeror must, at all times during the
performance of the Contract/Standing
Offer,hold a valid Facility Security Clearance at the
level of SECRET, issued by the Canadian
Industrial Security Directorate (CISD), Public Works and
Government Services Canada
(PWGSC).
2. The Contractor/Offeror personnel requiring access to
sensitive work site(s) must EACH hold a
valid personnel security screening at the level of
SECRET, granted or approved by
CISD/PWGSC.
3. Subcontracts which contain security requirements are NOT to
be awarded without the prior written
permission of CISD/PWGSC.
4. The Contractor/Offeror must comply with the provisions of
the:
(a) Security Requirements Check List and security guide (if
applicable), attached at Annex C
(b) Industrial Security Manual (Latest Edition).
Snow Clearing/Landscape Maintenance CFS Leitrim, 3545 Leitrim
Road, Ottawa EP305-150806/A
Hill, Cris Telephone No. 819-956-1343 Fax No. 819-956-3600
c••••••••@•••••.••.ca
-----------------------------------------------------------------
-----------------------------------------------------------------
--------
Technical and Financial Evaluation and Basis of Seclection
Technical and Financial Evaluation - mandatory requirements at
bid closing
(1) Mandatory Site Visit attendance;
(Mandatory) Security Clearance of Secret Status, at bid closing,
in accordance with Part 6, Security Requirements;
(3) (Mandatory) Part Time Gardener qualifications in accordance
with Part 3, Section 1: Technicial
Bid
(4) (Mandatory) Full Supervisor qualifications in accordance
with Part 3, Section 1: Technicial
Bid
(5) (Mandatory) Contractor's Experience and Past Performance in
accordance with Part 3, Section 1:
Technical Bid.
(6) (Mandatory) Employee Information for Security at bid
closing in accordance with Part 6, 6.2
(7) (Mandatory) Submission of Firm Price/Rates in Canadian funds
in accordance with Financial Bid Annex B;
Only proposals found to meet ALL the mandatory requirements will
be deemed acceptable proposals and will be further evaluated in
accordance with the evaluation criteria. Proposals not meeting
ALL of the mandatory requirements will be deemed non-responsive
and will be given NO further consideration.
Basis of selection
A bid must comply with the requirements of the bid solicitation
and meet all mandatory evaluation criteria to be declared
responsive.
The responsive bid evaluation will be based on the Lowest
Responsive Bid Price, a combination of the overall lowest total
bid of which 80% will be for the firm pricing (Pricing Schedule
1 and 2) and 20% on the "as and when" (Pricing Schedule 3, 4 and
5) will be recommended for award of a contract
Delivery Date: Above-mentioned
The Crown retains the right to negotiate with suppliers on any
procurement.
Documents may be submitted in either official language of Canada.
Get a plain-English breakdown of this tender — what they need, who can bid, how to approach it, and tips for small suppliers. Takes a couple of seconds.
Other federal contracts in the same classification, and who won them.
| Tender | Awarded to | Buyer | Value | Date |
|---|---|---|---|---|
| GROUND KEEPING AND SNOW REMOVAL AT NRC ROYALMOUNT BUILDING | M.P.R. NEIGEX INC. | National Research Council Canada | Not disclosed | 2022-11-18 |