Nature of Requirements:
Port Snout Engineering Study
31034-149492/A
Sole, Mike
Telephone No. - (250) 363-8444
Fax No. - (250) 363-3344
Email - m••••••••@•••••.••.ca
NOTICE AMENDMENT # 05
This amendment is raised to replace in its entirety all previous
solicitation and amendment documents in order to address
additional breakdown of work in Phase 1.
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
NOTICE AMENDMENT # 04
Issued to extend the solicitation closing date to Oct21/14.
NOTE: a further amendment is to follow to adjust the components
of Phase 1.
NOTICE AMENDMENT # 03
Issued to extend the solicitation closing date to Oct14/14.
NOTICE AMENDMENT # 02
Issued to extend the solicitation closing date to Oct03/14 and
remove the Canadian Content requirement in accordance with the
attached solicitation.
NOTICE AMENDMENT # 01
Issued to extend the solicitation closing date to Sept30/14 in
accordance with the attached solicitation.
The National Reseaarch Council (NRC) requires research and
development services in support of feasibility testing on the
NFIRAOS / IRIS interface design. (This will include testing
mechanical and thermal performance of proposed interface design
via the prototyping of key elements. As described in the
documents, NRC Herzberg will design and build several critical
components used within this interface while the successful
bidder designs the other elements as required.
Contractors bidding on this requirement must meet the required
delivery dates as these are essential towards Canada meeting its
deliverables towards the set timelines of the TMT project
office.
PROTOTYPE SNOUT TEST
The goal of this phase is proof of design concepts of the
elements of the Optics Enclosure by prototype testing. By
building and testing the Port Prototype, this will verify the
feasibility of the fabrication concept for ENCL panels and its
thermal performance. Similarly, the prototype test will also
verify the proposed instrument (snout) port design and
instrument exchange process will be tested.
The requirement is subject to the provisions of the Agreement on
Internal Trade (AIT).
The National Research Council has determined that any
intellectual property rights arising from the performance of the
Work under the resulting contract will belong to Canada, on the
following grounds:
The main purpose of the contract, or of the deliverables
contracted for, is to deliver a component or subsystem that will
be incorporated into a complete system at a later date, as a
prerequisite to the planned transfer of the complete system to
the private sector, through licensing or assignment of
ownership, for purposes of commercial exploitation.
Additional technical documents are available as specified in the
solicitation.
This office of Public Works and Government Services Canada
serves the public in English.
Delivery Date: Above-mentioned
The Crown retains the right to negotiate with suppliers on any
procurement.
Documents may be submitted in either official language of Canada.