Notice of Proposed Procurement
The National Research Council of Canada (NRC) requests proposals from qualified contractors for a feasibility study on the replacement of an aircraft door hangar, with the potential for the reuse of construction materials, and optional services including inspection, concept design, engineering drawings, Class D estimates, and construction.
The Contractor will develop three conceptual design options, including all relevant architectural and engineering development options:
1. Replace only necessary parts/equipment to return doors to reliable operating condition;
2. Replace only the necessary parts/equipment to restore the doors to a reliable operating condition and improve the thermal performance of the doors;
3. Complete replacement of doors (thermally broken, highly insulated and airtight)
4. Design and Cost Estimation
In order to meet the objectives outlined as part of the Feasibility Study development, the Contractor shall, at a minimum, conduct the following:
1. Prepare three high-level, feasible conceptual options to meet project requirements;
2. Prepare complete a comparative evaluation of all available options and formulate a
recommendation regarding the preferred option, taking into account the overall objectives and
requirements of the project;
3. Capital costs, operation and maintenance costs, code analysis, accessibility analysis, sustainable
design assessment, and security analysis. Use the information from this analysis to inform the
decision on which preferred option is best for our NRC;
4. Note: All options must be weather sealed to provide a tight and continuous seal when the
hangar door is closed. A robust energy and life cycle cost analysis will be used to evaluate these
options. The option with the greatest greenhouse gas (GHG) reduction potential, while
maintaining lower life cycle costs compared to the base case, will generally be the preferred
option. However, direction will be provided by the National Research Council (NRC) on the
selected option for implementation.
The Feasibility Report should contain the following:
1. A thorough site inspection:
2. Comprehensive feasibility study report;
4. The contractor is responsible for including the following elements in the project documentation:
5. Phase 3 (Optional): Construction
Mandatory Site Visit
Submission of Bids
Questions
All enquiries must be submitted in writing to the Contracting Authority no later than five (5) days before the bid closing date. Enquiries received after that time may not be answered.
The Contracting Authority for the Contract is:
Name: Johnathon Gillis
Title: Contracting Authority
National Research Council Canada
Directorate: Procurement and Contracting Services
Address: 1200 Montreal Road, Ottawa, ON, K1A 0R6
Telephone: (343) 552-5124
E-mail address: j••••••••@••••••••.••.ca