Title: Aggregate and Riprap Production - Km 262 to Km 922 Alaska Highway, BCLocation: Km 262 to Km 922 Alaska Highway, BC
Work Description: The work under this contract generally comprises of the following (including Optional work which may not be undertaken by PSPC) but is not limited to: Crushing, hauling, and stockpiling 16.0mm B.S.T. aggregates, 12.5mm sanding aggregates and riprap. Supply crawler tractor complete with ripper and 260-359 FWHP for pit clean-up after completion of crushing aggregates. Fort Nelson is located at km 455, on the Alaska Highway, BC. Drawing 001 shows the pit locations and quantities.Optional Work (Unit Price Table – Optional Work) may be awarded to the
Contractor at any time during the work at the sole discretion of the Departmental Representative. Optional Work shall be undertaken by the Contractor upon receipt of a signed Change Order.Work under this contract has to be completed by March 20, 2025