The work under this contract involves the reconstruction of a structure 401 located at Abrams Village, Prince Edward Island. The work includes but is not limited to:Removal of existing wharf and disposal of material, as shown on the drawings. Supply and installation of new Berlin Wall including h-piles, precast concrete panels, steel tie rods, anchor wall/blocks, and associated infilling for marginal wharf.Supply and install new wharf stem and ell structure made up of steel H-Piles and timber fender piles.Supply and placement of reinforced concrete deck.Supply and installation of wharf accessories including mooring holdfasts, HSS wheel guard and ladders.Construction of approach ramp from service are to marginal wharf.Electrical work as detailed on drawings including light poles.Supply and placement of new electrical building. The Contractor shall perform and complete the Work by November 1, 2027. The estimated cost for this opportunity is within the following cost category: between $5,000,001 to $20,000,000.