WORKSITE LOCATION
Sooke, British-Columbia
DELIVERABLES / SCOPE OF WORK
The scope of work consists of the furnishing of all plant, labour, equipment, and material for float repairs in Sooke Small Craft Harbour, B.C. The work will be completed in strict accordance with the specification and accompanying drawings, and subject to all terms and conditions of the Contract. The project work will consist of, but will not necessarily be limited to, the following:
Medium marine float construction work above and below seawater.
Supply, remove and replace float timbers such as decking, bull rail, fascia, flanges and mooring wells.
Supply and installation of UHMW rubstrips in mooring wells.
Installation of Owner supplied pontoons.
Supply all hardware.
EXPECTED START AND COMPLETION DATES
The services of the Contractor will be commencing upon contract award. The expected completion date of this project is December 30th, 2016.