LOCATION OF WORK
Oshawa Harbour, Ontario
DELIVERABLES / SCOPE OF WORK
Work under this contract includes, but is not limited to, the provision of all labour, materials, and equipment required to:
1.Procure surveyor to complete layout of the project site;
2.Design, supply and install foundations for two new AtoN (Aid to Navigation) towers;
3.Design and construct a culvert style entrance into the site and gravel access-way running to both new AtoN tower locations;
4.Fabricate two AtoN towers;
5.Transport two AtoN towers to the site;
6.Pick up day-marks and associated hardware from CCG and install on new towers;
7.Erect the new AtoN towers, along with the supplied navigational day-mark;
8.Remove to grade and dispose of the existing rear range;
9.Execute close-cut clearing of vegetation in the area to establish visibility corridor;
10.Restore the site as necessary; and,
11.Erect and maintain any and all measures required to complete the works in consideration of the reasonably anticipated weather conditions during the construction period.
Work excludes:
1.Installation of lanterns and associated equipment.
2.Supply of lanterns, day-marks and associated equipment.
FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings to review and verify the form, nature and extent of the work, materials needed for the completion of the work, the means of access to the site, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies and other circumstances which may influence or affect their bid or costs to do the work. No allowance shall be made subsequently in this connection on account of error or negligence to properly observe and determine the conditions that will apply. Contractors, bidders, or those they invite to site are to review the specification Section 013530 "Health and Safety Requirements" before visiting site. They must also contact the Oshawa Harbour Authority to be granted access.
EXPECTED START AND COMPLETION DATES
The services of the Contractor will be commencing upon contract award. The expected completion date of this project is March 31, 2018.