SCOPE OF WORK / DELIVERABLES:
The work consists of the furnishing of all plant, labour, equipment and material for slipway repairs in Puffin Island, NL, in strict accordance with specifications and accompanying drawings and subject to all terms and conditions of the Contract.
In general, work under this contract consist of but will not necessarily be limited to the following:
1. Removal of the dilapidated section of the existing slipway (combination of reinforced concrete support pedestals and treated timber wood construction), as noted on the drawings.
2. Supply and installation of new slipway, complete with concrete levelling pad, dowelled bars, reinforced concrete deck topping, and timber beams/runners, as noted on the drawings.
3. Supply and installation of treated dimension timber beams, runners wheelguard and wheelguard blocking, as noted on the drawings.
SPECIAL CONSIDERATIONS:
Bidders should note and pay special attention to the Environmental Assessment related to this requirement. All recommendations MUST be respected and followed as the work outlined in the specifications is completed.
FAMILIARIZATION WITH SITE:
Two site visits will be held, attendance at one of the two is Mandatory.
Option #1 will be held on Wednesday June 22 2016.
Option #2 will be held on Friday June 24 2016.