The scope of work for this project is the provision of construction activities for the shoreline protection repairs at Musgrave Harbour, NL.
FAMILIARIZATION WITH SITE
Before submitting a bid, it is recommended that bidders visit the site and its surroundings, at their own expense and schedule, to review and verify the form, nature and extent of the work, materials necessary for the completion of the works, the means of access to the site, severity, exposure and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account of error or negligence to properly observe and determine the conditions that will apply.
Take all appropriate safety measures for any visit to site, either before or after acceptance of bid.
PERIOD OF WORK
The period of work will be from contract awarded for a period of 20 weeks.
TWO PHASE SELECTION PROCESS
This is the first phase (Phase 1) of a two-phase competition: the first phase will evaluate the qualifications of all bidders; second phase (Phase 2) will invite the qualified bidders to provide a financial bid on the project based on the specifications and drawings. Upon award of contract in Phase Two the pre-qualification list will be terminated, no additional contracts will be awarded.