The scope for this project consists of construction activities to complete a repair to the existing wharf and to restore the structural integrity to the infrastructure. In general, the Work will consist demolition and removal of an approximately 6.1m long by 9.1m wide section of creosote timber cribwork, and all associated components. Reinstatement of new timber cribwork, including reinforced concrete deck, and all associated components. All work to be completed as per the associated project drawings and specifications.The Contractor must perform and complete the Work by 30 April, 2023.