This Statement of Work (SOW) provides an overview of the general requirements for the replacement of Primary Chiller #3, hereafter referred-to as the “Backup Chiller” project, to be undertaken at the High Commission of Canada (HCC), New Delhi India.
In addition to the replacement of the Primary Chiller, the existing Co-Gen/Absorption Chiller system is no longer required or operable and has been decommissioned for a number of years. In order to plan for, and utilize the service Building space that is currently housing the equipment and associated piping, etc. for upcoming future chiller-related projects, it is necessary to remove and restore the locations where the Co-Gen equipment is currently housed at the High Commission of Canada.
A detailed mechanical and electrical design and specification package has been prepared in to ensure that all Co-Gen equipment and
components are appropriately removed and all current connections to the backup power generation system and the chiller system are
appropriately reinstated.