Tender available date: Tuesday, July 14, 2026.
Tender closing date: Tuesday, August 18, 2026.
Project Inquiries: Bijhan Chaglani, Project Procurement Officer, Alberta Transportation and Economic Corridors. E-mail: Bijhan.Chaglani@gov.ab.ca.
TENDERS will only be received by email at trans.tender@gov.ab.ca, before 2:01:00 P.M., for construction of the following work:
TND0025870
BRIDGE REHABILITATION AND OTHER WORK HWY 11:10
88:18 BF 78194-1 - Carrying Hwy 88 over Bear River, 26 Km SE of Fort Vermilion
PEACE REGION
APPROXIMATE QUANTITIES:
130 Day Lane Closure for Bridge Construction
1 Lump Sum Traffic Accommodation for Bridge Construction
90 Square Metre Partial Depth Repair - Girder Top Flanges and Shear Keys
70 Cubic Metre Deck Overlay Concrete - Supply - Fibre-Reinforced HPC Concrete
588 Square Metre Deck Overlay Concrete - Place
29 Cubic Metre Concrete (Class HPC) - Supply and Place
48 Metre Drain Troughs
1 Lump Sum Miscellaneous Repairs
Contractor to supply all materials.
Contract Completion Date: September 15, 2027.