The Laboratory Centre for Disease Control is occupied by Health Canada and located at 100 Eglantine Driveway in the Tunney’s Pasture complex, was constructed in 1954/55. The building is a low-rise office laboratory facility with irregular configuration of four rectangular blocks of three (3) stories each.
The objective of this requirement is to have a Contractor implement the Construction Phases throughout all three (3) floors of LCDC building. The Contractor will complete the construction changes, updates and modifications as shown in the 100% stamped Architectural Mechanical and Electrical drawings package and National Master Specification. Each and every phase of the project is to be completed by the Contractor as per the schedule provided in the Statement of Work. All construction work must take place between 17:00 to 24:00 during weeknights and any time on the weekends and statutory holidays.