This Work includes the supply of all labour, materials, equipment and services required to complete the construction of shared pathways, on-street bike lanes, and local street bikeways.
The Work includes, but is not limited to the following:
Mobilization and demobilization
Traffic and pedestrian accommodation and staging
Work Site management including temporary construction facilities, security, and protection of existing utilities
Tree protection and tree preservation plans
Removal of existing concrete walk, curb and gutter, curb ramps, median islands, etc.
Earthworks and regrading of existing landscaped areas.
Construction of new asphalt and concrete shared pathways
Construction of new concrete sidewalks, curb and gutter, v-gutter, curb ramps, median islands, slab-on medians, and commercial crossings
Construction of continuous crossings
Pavement milling and overlay, road reconstruction, and gutter fill
Removal, abandonment, and installation of drainage infrastructure including catch basins, catch basin manholes, CB/CBMH leads, and perched manholes
Removal, relocation, and installation of street lights
Removal and installation of chain link fencing
Landscape remediation of disturbed areas including topsoil and sod
Tree planting
Work Site cleanup
Warranty and maintenance
Final inspection and Contract closeout