Project Description
Big Bay location is located on the shore of Georgian Bay, less than 20km northeast of Wiarton, within the Township of Georgian Bluffs.
The work consists of, but not limited to, the following:
Encapsulating the existing timber crib wharf with steel sheet piling;
Installing a new steel pile cap on sheet pile walls;
Installing new safety ladders;
Removing the existing timber fenders, and installing new fenders;
Installing a new concrete deck.FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings, at their own expense, to review and verify the form, nature, and extent of the work, materials needed for the completion of the work, the means of access to the site, severity, exposure, and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies, and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account or error or negligence to properly observe and determine the conditions that will apply.
Contractors, bidders, or those they invite to site are to review specification Section 01 35 29 – Health and Safety Requirements before visiting site. Take all appropriate safety measures for any visit to site, either before or after acceptance of bid.