An Advance Contract Award Notice (ACAN) is a notification through the open bidding methodology of the intent to award a directed contract.An Advance Contract Award Notice (ACAN) allows departments and agencies to post a notice, for no less than fifteen calendar days, indicating to the supplier community that it intends to award a good, service or construction contract to a pre-identified contractor. If no other supplier submits, on or before the closing date, a statement of capabilities that meets the requirements set out in the ACAN, the competitive requirements of the government’s contracting policy have been met. Following notification to suppliers not successful in demonstrating that their statements of capabilities meets the requirements set out in the ACAN, the contract may then be awarded using the Treasury Board’s electronic bidding authorities.If other potential suppliers submit Statements of Capabilities during the fifteen calendar day posting period, and meet the requirements set out in the ACAN, the department or agency must proceed to a full tendering process on either the government’s electronic tendering service or through traditional means, in order to award the contract.
Applicability of trade agreements and other obligations:
The resulting contract will not be subject to any trade agreements or other obligations.
Objective of the ACAN:
Provide quarterly and annual preventive maintenance service for a two circuit 290 TON SMARDT Chiller over a period of five consecutive years at AAFC Fredericton Research and Development Centre. Warranty includes unplanned maintenance resulting from pre-mature component failure and a flange to flange warranty for a period of five years from equipment start-up date.
Statement of Work: rly Inspections to be performed:
Chiller Compressor
Inspect for any mechanical damage to compressors
Perform vibration analysis of mechanical components
Inspect and test main power supply
Perform tightness & secureness (T&S) test on main power supply terminals
Perform electrical connections hotspots / discoloration test
Measure amperages against design specs. Adjust/Calibrate if necessary
Measure DC bus voltage against design specs.
Test communication cables for secured and tight connections
Inspect physical condition of exposed printed circuit boards (PCBs)
Inspect and clean all PCB's for dust build up and corrosion
Download all compressor fault and event logs.
Perform trend analysis or engage factory for analysis if necessary
Calibrate all compressor suction and discharge Pressure/Temperature sensors
Perform ice bath test where necessary
Ensure all compressor IGV's are operational and functioning properly
Ensure compressor safeties are functional (HP, LP, Low temp cutout)
Chiller Controls
Perform function tests on chiller controller and touch panel operation
Measure control voltages against design spec
Inspect and clean control I/O PCB
Perform T&S test all control terminals
Ensure all control cabinet heating/cooling fans are operating within normal range
Measure and compare power on primary and secondary of control transformer against
design spec
Perform chiller operation and control sequence and verify normal functions
Download chiller controller event / data logs and settings
Perform trend analysis or engage factory for analysis if necessary
Chiller Vessel & Electrical
Leak check chiller with electronic leak detector
Visually inspect refrigerant level using evaporator site glass and motor cooling site glass
Visually inspect motor cooling line hoses for any signs of cracking
Check operation of electronic level sensor and calibrate if necessary
Perform function test on electronic expansion valves
Calibrate water temperature sensors (perform ice bath test if necessary)
Check evaporator approach and confirm against design specs
Check Condenser approach and confirm against design specs
Inspect evaporator and condenser water flow devices
Perform function tests as required
Inspect main disconnect and chiller power terminals and line reactors
Inspect heat trace is operational (if provided)
Visually inspect chiller for loose cables, paint issues, insulation wear, etc.
Repair as necessary or submit IR for repair on next inspection
Using refractometer, verify glycol percentage per specification (if chiller required glycol).
Annual Inspections to be performed:
Condenser Tube Brushing
Drain Condenser
Brush Condenser tubes
Install new condenser gasket
Place chiller back in operation
Chiller Compressor
Perform Quarterly Inspection
Chiller Controls
Perform Quarterly Inspection
Chiller Vessel and Electrical
Perform Quarterly Inspection
Cost: The total value of the contract will be 31,826.30$. (Tax included)
Deadline: The required activities will start to contract award.
Proposed supplier: Smardt Inc.
1840 Trans Canada HighwayDorval, Quebec, H9P 1H7
Justification for use of a single-source supplier:
The chiller uses a specialized magnetic bearing technology. The result is a highly efficient chiller with cutting edge technology requiring specialised service. The product manufacturer offers a flange to flange extended warranty coverage which includes unplanned maintenance resulting from premature component failure for the chiller. This warranty will be in effect for five years from the equipment start-up date only if maintained by the original equipment manufacturer. They will provide preventive maintenance and inspection work during the warranty period.
Suppliers’ right to submit a Statement of Capabilities: Suppliers who consider themselves fully qualified and available to provide the services and warranty coverage described herein, may submit a statement of capabilities in writing to the contact person identified in this Notice on or before the closing date of this Notice. The statement of capabilities must clearly demonstrate how the supplier meets the stated requirements.
Closing date for the submission of the Statement of Capabilities:
April 20, 2016 at 2:00 p.m. (Eastern Daylight Time)
Inquiries and Submission of Statements of Capabilities: requests for information shall be submitted IN WRITING to the contracting authority:
Angela Quan
Procurement and Contracting Officer
Agriculture and Agri-Food Canada
2001 Robert-Bourassa Blvd, suite 671 TEN
Montreal QC H3A 3N2
A••••••••@•••.••.ca