WORK SITE LOCATION
Cape St. Francis, Pouch Cove, NL
DELIVERABLES / SCOPE OF WORK
The work consists of the furnishing of all plant, labour, equipment and material for equipment building and helipad reconstruction at Cape St. Francis in Pouch Cove, NL. All work to be carried out in strict accordance with specifications and accompanying drawings and subject to all terms and conditions of the Contract.
Work under this contract includes but is not limited to:
“Gut” of the interior of the building, as noted on the drawings.
Removal and replacement of the exterior metal siding and door.
Refurbishment of the security gate at the entrance to the site.
Electrical work, as noted on the drawings.
MANDATORY SITE VISIT
It is mandatory that the Bidder or a representative of the Bidder visit the work site. The site visits will be held on Wednesday, August 30, 2017 and Thursday, August 31, 2017. Bidders must attend one (1) of the two (2) sessions offered.
Bidders must communicate with the Contracting Authority no later than one (1) business day prior to confirm attendance and provide the name(s) of the person(s) who will attend. Bidders will be required to sign an attendance sheet. Bidders should confirm in their bid that they have attended the site visit. Bidders who do not attend the mandatory site visit or do not send a representative will not be given an alternative appointment and their bid will be declared non-responsive. Any clarifications or changes to the bid solicitation resulting from the site visit will be included as an amendment to the bid solicitation
EXPECTED START AND COMPLETION DATES
The services of the Contractor will be commencing upon contract award. The expected completion date of this project is November 3, 2017.