A complete refurbishment is required for 7 Hanover House, 20 Hanover House, and 40 Hanover House on St John's Wood High Street, London, UK, NW8 7DX. No structural changes or alterations are planned, but we will be renewing the electrical; heating; plumbing; flooring; kitchens and bathrooms followed by a complete redecoration (repainting) and clean.
Hanover House is a building which contains a number of flats and was constructed in the 1930’s. The internal layouts of the three flats have seen little change since and this also applies to the plumbing system in particular. Indeed several flats share the same continuous plumbing system. The flats have been redecorated and maintained regularly by the Canadian High Commission, but this will be the first major refurbishment for many years where it is the intention to remove most finishing’s, bathrooms, kitchens and carryout a total mechanical and electrical upgrade.
The managing agents will provide the necessary licenses under landlord management and the Canadian High Commission will carry out an asbestos survey as soon as the flat becomes vacant. The results will available for review prior to the commencement of this project. It is the intention for all asbestos to have been removed or made safe prior to any works on site under this SOW.
The flats will be empty and unfurnished.
Bidders must (mandatory) visit the site on October 24, 2019 at 12:00 PM British Summer Time (BST), at their own expense, to become familiar with all of its on-site conditions.
No expenses related to the site visits will be reimbursed.