SCOPE OF WORK / DELIVERABLES
Work under this Contract includes but is not limited to the provision of all labour, materials, and equipment required to:
Mobilize to site with a work barge of appropriate size and certification;
Salvage:
Existing ATON appurtenances (lanterm, solar panels, batteries and battery box); and,
Existing ATON tower.
Remove and dispose of existing hand rails (building and pier cap);
Remove and dispose surplus abandoned utilities;
Demolish and remove existing building;
Complete pier repairs as detailed, including:
Partial depth removal of existing concrete;
Concrete patching; and,
Concrete crack sealing.
Install new reinforced concrete foundation above existing pier cap.
Install new 9.75m ATON towerTower has been fabricated with a splice ring and may be installed in two sections.
Install salvaged ATON equipment (Lantern/Solar Panels/Batteries).
Demobilize.
The following work will be undertaken by others and is hereby excluded:
EXPECTED START AND COMPLETION DATESThe services of the Contractor will be commencing upon award of the contract. The expected completion date of this project is October 31, 2017.
Question and Answer period: DFO will accept questions from Bidders until Wednesday, July 19th 2017. These are to be sent directly and only to the contracting Officer listed below.
Enquiries regarding this Invitation to Tender are ONLY to be submitted in writing by emailing to the following: