Nature of Requirements:
SUPERVISION WORKS FOR THE RECONSTRUCTION OF THE FISHERMEN'S
WHARF IN MINGAN, QC
PROJECT DESCRIPTION
The work included in this project include the supervision of the
reconstruction works of the fishermen's wharf in Mingan,
North-Shore, QC.
More precisely, the work includes the following :
Installation of steel and timber piles on a sandy bottom;
Construction of a structural slab supported by the piles;
Set-up of on-wharf services (water, electricity, lighting,
winch, mooring bollards);
Excavation of sediments for dredging;
Construction of a parking lot and wharf access lane;
Relocation of a waste oil tank and installation of a service
shed;
Demolition of the remains of the old wharf.
MANDATORY CRITERIA AT CLOSING DATE
Licensing, Certification or Authorization;
Provide consultant team identification;
Provide Declaration/Certifications form.
MANDATORY CRITERIA PRIOR TO CONTRACT AWARD
CODE OF CONDUCT CERTIFICATIONS - CONSENT T0 A CRIMINAL RECORD
VERIFICATION:
Bidders must provide with their bid or promptly thereafter a
complete list of names of all individuals who are currently
directors of the Bidder. If the required names have not been
received by the time the evaluation of bids is completed, Canada
will inform the Bidder of a time frame within which to provide
the information. Failure to comply will render the bid
non-responsive.
Canada may, at any time, request that a Bidder provide properly
completed and Signed Consent Forms (Consent to a Criminal Record
Verification form - PWGSC-TPSGC 229) for any or all individuals
aforementioned within the time specified. Failure to provide
such Consent Forms within the time period provided will result
in the bid being declared non-responsive.
RATED REQUIREMENTS
Achievements and experience of Proponent on Project management
in marine construction;
Achievements and experience of prime consultant or Key
Sub-consultants and Specialists on construction supervision in
marine projects;
Achievements of Key Personnel on Projects;
Understanding of the Project;
Scope of Services;
Management of Services.
PERIOD OF WORK
Construction schedule is planned for 44 weeks from the contract
award date.
BUDGET
The budget, for this project, is between 250 001 $ and 500 000 $
INQUIRIES
All enquiries regarding this tender, are to be submitted in
writing to the Contractual Authority : Jean Rochette, Supply
Specialist at j••••••••@•••••.••.ca.
TENDER DOCUMENTS
Firms intending to submit tenders on this project should obtain
tender documents through the MERX service provider
(http://www.merx.com). Drawings and specifications are now
available for viewing and downloading in PDF format or in hard
copy. Bidders should take note that attachment 1 (ATT 1)
contains the full set of drawings and specifications, which
consist of PDF files organized in an industry-standard directory
structure. Addenda, when issued, will be available from the MERX
service provider. Firms that elect to base their bids on tender
documents obtained from other sources do so at their own risk
and will be solely responsible to inform the tender calling
authority of their intention to bid.
BID RECEIVING
Sealed tenders will be received in English or French at the
address mentioned below.
LANGUAGES
This PWGSC office provides acquisition services to the public in
both official languages.
Ce bureau de TPSGC fournit des services d'achat au public dans
les deux langues officielles.
Delivery Date: Above-mentioned
The Crown retains the right to negotiate with suppliers on any
procurement.
Documents may be submitted in either official language of Canada.