LOCATION OF WORK :
Courtenay, British-Colombia
EXPECTED START AND COMPLETION DATES :
The services of the Contractor will be commencing upon contract award. The expected completion date of this project is March 31, 2017.
FAMILIARIZATION WITH SITE :
No mandatory site visit is required.
DELIVERABLES / SCOPE OF WORK :
Fisheries and Oceans Canada is inviting bids for the improvement of the existing hydraulic system at Puntledge Hatchery in Courtenay. The proposed upgrades are designed to improve the insufficient flow in the current system by installing new supply water mains, piping, and associated infrastructure. The scope of the hydraulic upgrades includes installing new PVC piping with associated infrastructure, replacing existing Tee connections on existing PVC piping and installing new supply water mains and associated infrastructure.
Work under this Contract includes but is not limited to the provision of all labour, materials, and equipment required to:
Install approximately 50m of Ø300 PVC piping and associated infrastructure. (Gate Valves, etc.)
Replace two existing Tee connections on an existing Ø500 PVC pipe with new PVC Wyes.
Install supply water mains and associated infrastructure as indicated in the contract drawings and specifications.